How Do I Set Up a Chain of Timesheet Approvers?



Microsoft Project Server Frequently Asked Questions (FAQs): Overview



Microsoft Project Server Frequently Asked Questions (FAQs): Details

Background Information

In Project Server 2007, the Timesheets for each resource must be submitted to the person designated as each resource's Timesheet approver, who must then approve or reject the Timesheet. It is easy to set up a single person as the Timesheet approver for any resource by editing the resource in the Resource Center page and selecting any resource manager as that resource's Timesheet Manager. What is more difficult, however, is to set up a "chain" of Timesheet approvers.

Resolution

Before I show you how to set up the chain of Timesheet approvers, consider the following list of people:

Senior Manager A

    Resource Manager A

        Team Member A

In the preceding list, Team Member A must submit a Timesheet to Resource Manager A for approval. Once approved, Resource Manager A must submit Team Member A’s timesheet to Senior Manager A for final approval. To set up this process, the Project Server administrator must create a new custom Group named something like Timesheet Reviewers using the following steps:

1. Log into PWA with administrator permissions.

2. Click Server Settings > Manage Groups.

3. Click the New Group button.

4. Name the Group something like Timesheet Reviewers.

5. Add Resource Manager A to the new Group.

6. In the Categories section, add the My Resources category to the list on the right.

7. In the Permissions for My Resources grid, select the Resource Managers template and click the Apply button.

8. In the Permissions for My Resources grid, DESELECT the Allow option for the Approve Timesheets permission (DO NOT select either Allow or Deny; leave them both unchecked).

9. In the Global Permissions grid, select the Resource Managers template and then click the Apply button.

10. Click the Save button.

The above set of steps allows Resource Manager A to accept Timesheets from his/her resources and give interim approval to Timesheets. IMPORTANT NOTE: If Resource Manager A is also in the Resource Managers group, the Project Server administrator MUST remove him/her from the Resource Managers group.

Next, the Project Server administrator must set up the "chain" of approvals as follows:

1. Navigate to the Resource Center page.

2. Select Senior Manager A, Resource Manager A, and Team Member A.

3. Click the Edit Details button.

4. For Senior Manager A, add her to the Resource Managers group and the Executives group, and then click the Save and Continue button.

5. For Resource Manager A, add him to the Timesheet Reviewers group and set Senior Manager A as his Timesheet Manager.

6. Click the Save and Continue button.

7. For Team Member A, set Resource Manager A as her Timesheet Manager, then click the Save button.

Adding Senior Manager A to the Resource Managers group makes her the final Timesheet approver. Adding Resource Manager A to the new Timesheet Reviewers makes him an interim Timesheet approver who must submit the Timesheet to Senior Manager A for final approval.

 

Stay Connected

Join Our
LinkedIn Network
Follow Us
on Twitter

About FAQs

Microsoft Project Server Frequently Asked Questions (FAQs) provide information about Microsoft Project Server 2002, Microsoft Project Server 2003, Microsoft Project Server 2007, and Microsoft Project Server 2010.

Topics include common errors and the Project Server queue, project manager and resource manager approvals, enterprise calendars, enterprise custom fields, enterprise projects and the enterprise resource pool, user access, reports and OLAP analysis, resource work, project costing, task progress reporting and timesheets, Project Web Access (PWA) and Project Professional, check-out check-in and the local cache, saving and publishing, and issues risks deliverables documents and project workspaces.

About This Site

Project Server Experts (www.projectserverexperts.com) is an online community that provides answers to Project Server Frequently Asked Questions, allows members of the Project Server community to connect with one another by uploading their Business Cards, provides links to online Project Server resources, and links to Microsoft Project and Project Server related jobs.

This site is brought to you by MSProjectExperts. If you find the information posted here useful, please consider visiting our commercial site (www.msprojectexperts.com) for Project Server books, Project Server training and Project Server consulting services. Please support our sponsors. Thanks. -- The MSProjectExperts Team

Submissions

We welcome content submissions. We give author credit and cross link on all accepted articles. Please send your articles and suggestions to info(at)msprojectexperts.com.

Copyright

Reproduction of content on this site is strictly prohibited without the express permission of MSProjectExperts. Copyright (c) 2011 CHEFETZ LLC. All rights reserved