Resolution for Project
Server 2003
To forward a combined team Status Report to one or
more recipients, complete the following steps in Project Server 2003:
1. On the PWA
Home page, select the Status Report that has responses from your team members.
2. On the “View
Status Report Responses from your Team Members” page, click the Team Status
Report icon for the desired reporting period.
3. In the
combined report page, click the Zoom button.
4. In the new
Internet Explorer window containing the zoomed Team Status Report, click File >
Send > Page by E-mail.
5. Select the
recipients of the message and send it.
Alternately, instead of performing steps #4-5 above,
you can also click File > Save and then save the page as an HTML document.
Afterwards, you can upload the HTML document to any Document library in
SharePoint.
Resolution for Project Server
2007
To forward a combined team Status Report to one or
more recipients, complete the following steps in Project Server 2007:
1. Navigate to the Status Reports page in PWA and click the
name of your Status Report in the Requests section.
2. In the pane
at the top of the View Responses page, select the time period for which you wish
to see a combined team Status Report and then click the Apply button.
3. Click the row
header to the left of the first resource's name, press and hold the Shift key,
and then select the row header for the last resource (to select all of the
responses simultaneously).
4. Click the
Open button. You will now see a combined team Status Report with responses from
all people who reported to you during the selected reporting period.
5. Click the Export to Word button and save the combined
report as a Word document.
6. E-mail the
document to the intended recipients.