Resolution
Complete the following steps:
1. Navigate to
the View Resource Assignments page in PWA.
2. Select all
resources and then click the Apply button.
3. Make sure you
have the Summary view selected.
4. Click the
Filter, Group, Search tab.
5. Select the
AutoFilter option.
6. Click the
Filter, Group, Search tab again to collapse the options.
7. Scroll to the
Status field, click the AutoFilter button for that field, and then select the
"Changes Submitted" item.
The grid shows only those resources who have submitted
task updates and whose Project Managers have not yet
processed the updates into the Microsoft Project plan.