Resolution
To show the value as 100% in the task % Complete field
when the resources complete work on their task assignments, complete the
following steps:
1. Open any
project in which the % Complete is not calculating automatically.
2. Click
Tools - Options and select the Calculation tab.
3. Select
the "Updating task status updates resource status" option.
4. Click
OK.
From this point forward, Microsoft Project will
automatically calculate the task % Complete based on the actuals submitted by
team member on uncompleted tasks only. For those tasks completed prior to
changing the Options setting above, project managers must manually set those
tasks to 100% complete by double-clicking the completed task and entering 100%
in the Percent complete field.
Best Practice: Enable this setting in every
existing project and make sure that this is the default setting in every
enterprise project template as well.